Golestan
Supervision of dredging, river training, and diversion works on the Gorganrud River – Qaranjik
Introduction
A flood diversion canal was planned as part of the Gorganrud River project. Partial dredging was carried out during the 2019 flood event. Due to budget limitations, 119,000 m³ of excavation and 312,000 m³ of dredging were executed in this phase
BACK TO PROJECTS
CLIENT
CLIENT
Golestan Regional Water Company
LOCATIONGolestan
DATE OF COMPLETION2020
Copyrights © 2017 Sazeh Pardazi Iran Consulting Engineering Corporation. All rights reserved.